1. Separate official station weather from what happened on site
Always pull the nearest National Weather Service (NWS) or NOAA NCEI station observation alongside what your superintendent saw at the jobsite. Airport stations sometimes miss a localized cloudburst — recording both values with the station ID prevents anyone from claiming you guessed.
2. Tie the rain directly to a critical-path activity
Owners routinely deny weather extensions when interior work could have continued. State the exact critical-path activity stopped (e.g., "East footing pour stopped at 1:40 PM; 6 concrete crew and 2 electricians sent home at 2:15 PM").
3. Log drying/mud days separately
A half-inch of rain on Tuesday afternoon can make clay trench walls or subbase unworkable on Wednesday morning even under blue skies. Record saturated ground conditions and any competent-person excavation re-inspection under 29 CFR 1926.651(k)(1).