What do I have to write down for OSHA 29 CFR Part 1926?

Plain-English summaries (not the regulation itself) showing the written certifications, inspections, and JHAs each section points to. OSHA preliminary FY2026 Top 10 most frequently cited standards (updated Oct 5, 2026, osha.gov/top10).

OSHA Prelim FY2026 Top 10 · #9

29 CFR 1926.102 — Eye and face protection.

Requires employers to ensure each affected employee uses appropriate eye or face protection when exposed to flying particles, molten metal, liquid chemicals, acids or caustic liquids, chemical gases/vapors, or potentially injurious light radiation.

Paperwork: JHA PPE specification & inspection check

29 CFR 1926.201 — Signaling.

Requires flaggers and high-visibility warning garments conforming to MUTCD when signs, signals, and barricades do not provide necessary protection on or adjacent to a highway or street.

Paperwork: Spotter / flagger assignment in daily JHA

29 CFR 1926.251 — Rigging equipment for material handling.

Requires rigging equipment (slings, shackles, hooks) to be inspected prior to use on each shift and as necessary during use, and defective equipment removed from service immediately.

Paperwork: Pre-shift rigging inspection log; Custom lifting accessory proof-test marking

29 CFR 1926.352 — Fire prevention.

Requires moving combustibles away from welding/cutting areas (or shielding them), keeping suitable fire extinguishing equipment immediately available, and assigning fire watch when sparks can reach combustibles.

Paperwork: Hot work checklist & fire watch log

29 CFR 1926.404 — Wiring design and protection.

Requires ground-fault circuit interrupters (GFCIs) on all 120-volt, single-phase 15- and 20-amp temporary receptacle outlets on construction sites, or a written assured equipment grounding conductor program (AEGCP).

Paperwork: Written AEGCP & cord continuity test log (if not using GFCIs)
OSHA Prelim FY2026 Top 10 · #4

29 CFR 1926.451 — General requirements.

Covers scaffold capacity (4x intended load), full planking, safe access, fall protection above 10 feet (guardrails or PFAS), falling-object protection (toeboards), and competent-person inspections before each shift.

Paperwork: Pre-shift competent-person scaffold inspection tag/log

29 CFR 1926.453 — Aerial lifts.

Covers boom lifts and vehicle-mounted elevating work platforms: daily lift-control tests before use, standing firmly on basket floor (never climbing rails), wearing a body belt/harness with lanyard attached to the boom or basket, and respecting load limits.

Paperwork: Aerial lift pre-use daily inspection & control test checklist

29 CFR 1926.454 — Training requirements.

Requires each employee who performs work while on a scaffold to be trained by a qualified person, and each employee involved in erecting, disassembling, moving, operating, or inspecting scaffolds to be trained by a competent person.

Paperwork: Scaffold user & erector training roster
OSHA Prelim FY2026 Top 10 · #1

29 CFR 1926.501 — Duty to have fall protection.

Requires employers to protect employees on walking/working surfaces with an unprotected side or edge 6 feet or more above a lower level using guardrails, safety nets, or personal fall arrest systems. #1 most-cited OSHA standard (preliminary FY2026).

Paperwork: Pre-work surface structural integrity & fall-hazard check; Residential roof fall-protection method (or site-specific written plan under 1926.502(k) only if infeasible)

29 CFR 1926.502 — Fall protection systems criteria and practices.

Sets design and inspection criteria for guardrails (42 in ± 3 in toprail, 200 lb force), PFAS anchorages (5,000 lb per attached employee or qualified-person 2x safety factor), hole covers (2x load, secured, marked "HOLE"/"COVER"), and pre-use harness inspection.

Paperwork: Daily PFAS harness/lanyard/anchor inspection check; Prompt rescue plan documented on JHA
OSHA Prelim FY2026 Top 10 · #8

29 CFR 1926.503 — Training requirements.

Requires employers to train each employee who might be exposed to fall hazards using a competent person, and explicitly mandates a written training certification record (1926.503(b)). #8 most-cited OSHA standard (preliminary FY2026).

Paperwork: Written Fall Protection Training Certification Record

29 CFR 1926.601 — Motor vehicles.

Requires obstructed-view vehicles operating in reverse on jobsites to have a reverse signal alarm audible above surrounding noise OR an observer signaling it is safe to back up, plus pre-shift brake/steering/light checks.

Paperwork: Daily pre-shift equipment & backup alarm inspection check

29 CFR 1926.602 — Material handling equipment.

Covers earthmoving equipment (excavators, loaders, bulldozers, skid steers): seat belts/ROPS, working horns and reverse signal alarms when rear view is obstructed, and swing-radius/blind-spot controls.

Paperwork: Equipment pre-shift safety & exclusion-zone log

29 CFR 1926.651 — Specific excavation requirements.

Covers underground utility locates (811) prior to digging, safe egress (ladder/ramp within 25 ft in trenches 4+ ft deep), spoil piles kept at least 2 ft back from edges, water accumulation controls, hazardous atmosphere testing, and daily competent-person inspections.

Paperwork: 811 / underground utility locate ticket number & mark-out confirmation; Daily Competent-Person Excavation Inspection Log

29 CFR 1926.652 — Requirements for protective systems.

Requires cave-in protection (sloping, benching, shoring, or trench box/shield) for employees in excavations 5 feet or more in depth (or shallower if a competent person finds potential cave-in). Tabulated data for shields/shoring must be kept at the jobsite.

Paperwork: Manufacturer tabulated data on site during trench box / shoring use

29 CFR 1926.701 — General requirements.

Requires all protruding reinforcing steel (rebar) onto and into which employees could fall to be guarded to eliminate the hazard of impalement, and prohibits construction loads on concrete structures until qualified-person verification of strength.

Paperwork: Concrete pour log, cylinder breaks, and rebar cap inspection

29 CFR 1926.702 — Requirements for equipment and tools.

Covers concrete pumping systems (positive fail-safe pipe supports and coupling pins), powered trowels (deadman switch), concrete buckets (no riding, stay clear of suspended buckets), and lockout/tagout during mixer maintenance.

Paperwork: Pre-pour pump setup & hose whip-check verification

29 CFR 1926.850 — Preparatory operations.

Requires a written engineering survey by a competent person BEFORE demolition starts, shutting off/capping all electric, gas, water, steam, and sewer utilities, and shoring damaged walls/floors.

Paperwork: Written Pre-Demolition Engineering Survey; Utility shutoff / disconnect confirmation log
OSHA Prelim FY2026 Top 10 · #5

29 CFR 1926.1053 — Ladders.

Requires portable ladders accessing upper landing surfaces to extend 3 feet above the landing (or be secured with a grab device), 4:1 setup angle, non-conductive side rails near energized electrical, not using the top step of a stepladder, and competent-person inspections. #5 most-cited OSHA standard (preliminary FY2026).

Paperwork: Periodic Competent-Person Ladder Inspection Checklist & Defective Tag-Out Log

29 CFR 1926.1060 — Training requirements.

Requires employers to provide a training program by a competent person for each employee using ladders and stairways covering fall hazards, proper erection/placement, and maximum load capacities.

Paperwork: Ladder safety toolbox-talk sign-in sheet

29 CFR 1926.1153 — Respirable crystalline silica.

Protects construction workers cutting, grinding, coring, or drilling concrete/masonry from silica dust. Employers follow Table 1 engineering controls (integrated wet cutting or HEPA vacuum shrouds + required respirator APF) and must maintain a written Exposure Control Plan with a designated competent person.

Paperwork: Written Silica Exposure Control Plan; Competent-person silica inspection notes on daily report / JHA

29 CFR 1926.1400 — Scope.

Defines the scope of Subpart CC (power-operated equipment hoisting, lowering, and horizontally moving suspended loads), requiring qualified riggers, certified operators, signal persons, and power-line clearances.

Paperwork: Pre-lift JHA & lift plan (weight, radius, ground bearing, power lines, signal person)