Subpart CC — Cranes and Derricks in Construction

Paperwork for 29 CFR 1926.1400: Scope.

Plain-English summary (not the official rule): Defines the scope of Subpart CC (power-operated equipment hoisting, lowering, and horizontally moving suspended loads), requiring qualified riggers, certified operators, signal persons, and power-line clearances.
Competent person check: Crane/hoist lifts require certified operators, qualified riggers, and qualified signal persons under Subpart CC.

Written records & field paperwork

CitationDocument / RecordWhat to include
29 CFR 1926.1400(a) Pre-lift JHA & lift plan (weight, radius, ground bearing, power lines, signal person) Document load weight, crane capacity check, outrigger ground conditions, overhead power-line clearance (min 20 ft), and designated signal person.

Key paragraphs referenced

ParagraphSummary
1926.1400(a) Applies to power-operated equipment used in construction that can hoist, lower, and horizontally move a suspended load.

Templates & JHAs covering 29 CFR 1926.1400

Draft a Cited JHA Free