Subpart T — Demolition

Paperwork for 29 CFR 1926.850: Preparatory operations.

Plain-English summary (not the official rule): Requires a written engineering survey by a competent person BEFORE demolition starts, shutting off/capping all electric, gas, water, steam, and sewer utilities, and shoring damaged walls/floors.
Competent person check: A competent person MUST complete a written engineering survey prior to starting demolition operations (1926.850(a)).

Written records & field paperwork

CitationDocument / RecordWhat to include
29 CFR 1926.850(a) Written Pre-Demolition Engineering Survey Employer must have in writing evidence that a competent person performed an engineering survey of framing, floors, walls, and adjacent structures before demolition begins.
29 CFR 1926.850(c) Utility shutoff / disconnect confirmation log Document notification to utility companies and shutoff/capping of electric, gas, water, and sewer lines.

Key paragraphs referenced

ParagraphSummary
1926.850(a) Prior to permitting employees to start demolition, an engineering survey must be made by a competent person and the employer must have in writing evidence that such survey has been performed.
1926.850(c) All electric, gas, water, steam, sewer, and other service lines must be shut off, capped, or otherwise controlled outside the building line before demolition work is started.