OSHA 29 CFR 1926 Subpart T · Checked Nov 26, 2026

Selective & Structural Demolition JHA Template (OSHA 1926 Subpart T)

Pre-demolition and tear-out JHA highlighting the mandatory written engineering survey by a competent person (1926.850(a)), utility shutoff/capping, floor-opening covers, and dust/eye PPE.

Draft a JHA for Your Task (Free)

Includes Word (.docx), Excel (.xlsx), and PDF · Need just this JHA?

Draft for competent-person review: Walk the jobsite, adjust controls for actual conditions, and sign before work starts. Covers US federal 29 CFR Part 1926 only (state-plan states like CA, WA, and OR enforce extra rules). Not an OSHA compliance guarantee.

Steps, hazards & controls

Work Step Hazard Control 29 CFR 1926 Reference
Complete written engineering survey and disconnect utilities Unplanned structural collapse, gas explosion, or energized line strike Competent person completes and signs written engineering survey of framing, walls, and floors before work starts
Control level: administrative
Complete written engineering survey and disconnect utilities Unplanned structural collapse, gas explosion, or energized line strike Shut off, cap, or positively control all electric, gas, water, steam, and sewer services outside the demolition zone
Control level: elimination
Perform tear-out and protect exposed edges/floor openings Falls through floor openings or flying debris eye/face injuries Protect unprotected edges >= 6 ft and secure/mark covers (2x load) over all floor openings created during demo
Control level: engineering
Perform tear-out and protect exposed edges/floor openings Falls through floor openings or flying debris eye/face injuries Require ANSI Z87.1 impact eyewear with side shields (and face shield when prying/hammering overhead)
Control level: ppe

Competent person & paperwork

Competent person required: Yes

Employer MUST have written evidence of an engineering survey by a competent person before permitting employees to start demolition (1926.850(a)).

  • Written Pre-Demolition Engineering Survey (29 CFR 1926.850(a))
  • Utility Shutoff Confirmation Log (29 CFR 1926.850(c))

Baseline PPE

  • Hardhat
  • ANSI Z87.1 safety glasses + face shield
  • Cut-resistant gloves
  • Steel-toe puncture-resistant boots
  • N95/P100 respirator as needed for dust
Related OSHA 1926 guides: 1926.850 · 1926.501 · 1926.502 · 1926.102