Subpart P — Excavations

Paperwork for 29 CFR 1926.652: Requirements for protective systems.

Plain-English summary (not the official rule): Requires cave-in protection (sloping, benching, shoring, or trench box/shield) for employees in excavations 5 feet or more in depth (or shallower if a competent person finds potential cave-in). Tabulated data for shields/shoring must be kept at the jobsite.
Competent person check: Soil classification and protective-system design/selection require a competent person; excavations deeper than 20 feet require a Registered Professional Engineer (1926.652(b)/(c)).

Written records & field paperwork

CitationDocument / RecordWhat to include
29 CFR 1926.652(c)(2)(iii) Manufacturer tabulated data on site during trench box / shoring use Keep manufacturer tabulated data (or RPE design for >20 ft) at the jobsite while protective systems are being constructed/used.

Key paragraphs referenced

ParagraphSummary
1926.652(a)(1) Each employee in an excavation must be protected from cave-ins by an adequate protective system unless wholly in stable rock or less than 5 feet deep with competent-person verification of no cave-in potential.
1926.652(c)(2)(iii) At least one copy of manufacturer tabulated data identifying the registered professional engineer must be maintained at the jobsite during construction of the protective system.

Templates & JHAs covering 29 CFR 1926.652

Draft a Cited JHA Free