Scaffolding Erection & Use JHA Template (OSHA 1926 Subpart L)
Job Hazard Analysis for erecting, inspecting, and working on supported scaffolds above 10 feet: base plates, full planking, guardrails, safe ladder access, and daily competent-person tags.
Includes Word (.docx), Excel (.xlsx), and PDF · Need just this JHA?
Draft for competent-person review: Walk the jobsite, adjust controls for actual conditions, and sign before work starts. Covers US federal 29 CFR Part 1926 only (state-plan states like CA, WA, and OR enforce extra rules). Not an OSHA compliance guarantee.
Steps, hazards & controls
| Work Step | Hazard | Control | 29 CFR 1926 Reference |
|---|---|---|---|
| Prepare foundation and erect base frames | Scaffold tipping, settling, or structural collapse | Set all scaffold legs on base plates and mud sills over firm, level ground — never loose blocks or bricks Control level: engineering | |
| Prepare foundation and erect base frames | Scaffold tipping, settling, or structural collapse | Confirm scaffold and components are rated for at least 4x maximum intended load Control level: engineering | |
| Deck working levels, install guardrails, and set safe access | Falls through plank gaps, off open sides (>10 ft), or while climbing frames | Fully plank working levels between uprights using scaffold-grade planking Control level: engineering | |
| Deck working levels, install guardrails, and set safe access | Falls through plank gaps, off open sides (>10 ft), or while climbing frames | Install toprails, midrails, and toeboards on all open sides more than 10 ft above lower level Control level: engineering | |
| Deck working levels, install guardrails, and set safe access | Falls through plank gaps, off open sides (>10 ft), or while climbing frames | Provide attachable scaffold ladder or stair tower; prohibit climbing crossbraces Control level: engineering | |
| Pre-shift inspection and crew briefing | Crew using altered, incomplete, or weather-damaged scaffolding | Competent person inspects scaffold before each shift and updates green/yellow/red tag Control level: administrative | |
| Pre-shift inspection and crew briefing | Crew using altered, incomplete, or weather-damaged scaffolding | Confirm all scaffold users and erectors completed qualified/competent person training Control level: administrative |
Competent person & paperwork
Competent person required: Yes
Competent person must supervise erection/dismantling and inspect scaffold before each shift (1926.451(f)(3)).
- Scaffold user & erector training roster (29 CFR 1926.454(a)/(b))