OSHA 29 CFR 1926 Subpart Q · Checked Nov 26, 2026

Concrete Pour & Formwork JHA Template (OSHA 1926 Subpart Q)

JHA for footing, slab, and wall pours covering protruding rebar impalement caps, concrete pump pipe supports and hose whip checks, wet-cement alkali burn PPE, and trowel deadman switches.

Draft a JHA for Your Task (Free)

Includes Word (.docx), Excel (.xlsx), and PDF · Need just this JHA?

Draft for competent-person review: Walk the jobsite, adjust controls for actual conditions, and sign before work starts. Covers US federal 29 CFR Part 1926 only (state-plan states like CA, WA, and OR enforce extra rules). Not an OSHA compliance guarantee.

Steps, hazards & controls

Work Step Hazard Control 29 CFR 1926 Reference
Inspect formwork, rebar, and pump truck setup Rebar impalement or high-pressure concrete hose whip Cap or guard all protruding reinforcing steel onto or into which workers could fall to eliminate impalement
Control level: engineering
Inspect formwork, rebar, and pump truck setup Rebar impalement or high-pressure concrete hose whip Verify pump discharge pipe supports (100% overload design) and positive fail-safe coupling pins before priming pump
Control level: engineering
Place, vibrate, and finish wet concrete Chemical/alkali eye and skin burns from wet cement splash; struck by suspended bucket or runaway power trowel Wear ANSI Z87.1 splash-rated safety glasses/goggles, waterproof boots, and alkali-resistant gloves; stage eyewash station on site
Control level: ppe
Place, vibrate, and finish wet concrete Chemical/alkali eye and skin burns from wet cement splash; struck by suspended bucket or runaway power trowel Keep all crew out from underneath suspended concrete buckets during crane lifts
Control level: administrative
Place, vibrate, and finish wet concrete Chemical/alkali eye and skin burns from wet cement splash; struck by suspended bucket or runaway power trowel Verify manually guided power trowels have functioning deadman shutoff switches
Control level: engineering

Competent person & paperwork

Competent person required: Yes

Qualified/competent verification required before placing construction loads on cured concrete (1926.701(a)) and for formwork/shoring inspection.

  • Pre-pour formwork/rebar check on Concrete Daily Report

Baseline PPE

  • Rubber waterproof boots
  • Alkali-resistant rubber gloves
  • ANSI Z87.1 splash goggles/safety glasses
  • Long sleeves/pants
  • Hardhat
Related OSHA 1926 guides: 1926.701 · 1926.702 · 1926.102